9.1 Collating Example: Collate a booklet with Cover and Inside Pages using a 10-pocket collator.
Specifications: Collate 1 cover signature and 6 inside pages signatures using a 10-pocket collator. Setup time is 30 minutes overall and 5 minutes per pocket. Running rate is 3000 collated signatures per hour with a 2% slowdown per pocket.
9.1A Shop Standards (Collator Example)
Figure 9.1-1
Collator Example, Standards, Postpress Process
Comments (Fig. 9.1-1):
1. Costing Method: Finished Sheets. Program will not recognize signatures if set to Final Product.
2. 10 pockets, 2% slowdown per pocket.
3. 30 minutes setup + 5 minutes per pocket
9.1B Estimating/Order Entry (Collator Example)
Figure 9.1-2
Collator Example, Estimating/Order Entry, Cover Layout
Figure 9.1-3
Collator Example, Estimating/Order Entry, Inside Pages Layout
Figure 9.1-4
Collator Example, Estimating/Order Entry, Postpress Process
Comment (Fig. 9.1-4):
Select Bind All Components option.
Figure 9.1-5
Collator Example, Estimating/Order Entry, Analysis Report
Comments (Fig. 9.1-5):
1. Production Qty = 10,000/100 x 7 sigs = 70,000.
3. Run rate = 3000 x (100% - 7 pockets x 2% slowdown each) = 3000 x (86%) = 2580 collated booklets per hour.
4. Setup time: 30 minutes + 7 x 5 minutes/pocket = 65 minutes = 1.0833 hours.
5. Total time: 10,000/2580 = 3.8760 + 1.0833 = 4.9593 hours = 4.96 hrs.