This field will allow a user to determine when the system will spread the time for process across multiple days. For example, if the Time Break is set to 4 hours for a press process and the estimated time is 3.3 hours, the system will only load that press operation into one day. In other words, the system will look for a day that has sufficient time to complete the process in one day. If, however, the estimated time is over 4 hours the system will split the time across multiple days. If the field is set to “0” the system will ignore the entry.