In Plant Days

Updated March 31, 2023

Applies to : Prepress, Press, HSC/Digital, Postpress Processes

This option allows the user to automatically move the Job Due Date/Time from the Date/Time Ordered Date by the value in the field.

 

Prepress

 

Press

 

HSC/Digital

 

Postpress/Bindery

 

The value entered in this field will automatically adjust the Job Due Date/Time from the Date/Time Ordered Date.

 

 

Note:

* When an order has multiple processes with In Plant Days assigned the process that has the largest value will be used.

* If the In Plant Days is less then the default # of Days to Default Due Date then the default will take precedence.

* The In Plant Days does not have an affect on Scheduling other than to adjust the Job Due Date/Time.