Not dependent on previous operation

Updated May 25, 2024

Using this option will allow the Cost Center to be scheduled without regard to any previous operation's scheduled date. 

 

By default, the system will assume that the process is dependent unless option Not dependent on previous operation is selected.

 

For example; prepress processes like Preflight, generally do not have any operations that are required BEFORE them. Whereas Proofing could only occur AFTER Preflighting. In this case the Prepress Production Cost Center would NOT be depended on a previous operation. Proofing, however WOULD be dependent on the Prepress Production Cost Center being Completed at the Cost Center to continue.