Minutes for WTN

Updated Oct 26, 2022

Applies to : Press Makeready and Run Processes

Makeready

This field will allow the user to set additional Makeready time for jobs then have the imposition set as Work and Turn or Work and Tumble in the Layout tab.

 

 

The system will automatically include the extra time on the Makeready process line of an Estimate Analysis.

 

Press Run

The user also has the ability to set a default for the press process so that extra time is allotted for the production of jobs that have the imposition set as Work and Turn or Work and Tumble in the Layout tab.

 

 

In an estimate or order the user has the option to change the value on the press process.